EBRD will support US$39.5 million in hydropower rehabilitation projects in Bulgaria - 4th Annual International Summit and Exhibition: Hydropower Balkans
+44 207 394 30 90 (London)

EBRD will support US$39.5 million in hydropower rehabilitation projects in Bulgaria

Main » novosti » EBRD will support US$39.5 million in hydropower…

European Bank for Reconstruction and Development (EBRD) will support €37 million (US$39.5 million) in costs for rehabilitation projects at the Belmeken-Sestrimo-Chaira hydro complex and Vacha-1 hydropower facility in Bulgaria, according to an EBRD procurement update notice published on Jan. 18.

According to EBRD, Bulgaria’s state-owned National Electricity Co. (NEK) intends on using the proceeds of the grants provided by Kozloduy International Decommissioning Support Fund (KIDSF), which EBRD administers under grant agreement No. 049A. NEK will also use its own financial sources towards the rehabilitation.

KIDSF will provide 70% of the financing and NEK will fund the remaining 30%.
EBRD said the process will require procurement of activities such as design, manufacture, delivery, installation, supervision, setting, testing and commissioning of different equipment and systems for the following hydropower plants:

864-MW Chaira pumped storage

The rehabilitation includes plant control and monitoring system, relay protections, unit excitation system, vibration monitoring and analyses system of the units, generator/motor 19-kV switchgears and nodal 19-kV switchgears for control and protection of the units, service water feeding pumps, electric energy metering systems, ventilation systems, common auxiliary equipment and materials; disassembly, machining and installation of components of the turbine equipment and the automatic speed and active power regulation system of the units.

75-MW Belmeken pumped storage

The rehabilitation includes local automation equipment and oil pressure systems for control of spherical valves and their auxiliary valves, local automation equipment and oil pressure systems for control of mechanical brakes, nozzles, needles, deflectors and hydraulic cylinders of the deflectors, unit excitation systems, local automation equipment and oil pressure system for control of the gear-type couplings, speed governors and work stations, control systems and generator circuit breakers.

240-MW Sestrimo

Local automation equipment and oil pressure systems for control of the spherical valves and their auxiliary valves, local automation equipment and oil pressure systems for control of mechanical brakes, nozzles, needles, deflectors and hydraulic cylinders for the deflectors, unit excitation systems, speed governors and work stations, control systems and service water units (pump and motor) for generator cooling.

120-MW Momina Klisura

The rehabilitation will include local automation equipment and oil pressure systems for control of the spherical valves and their auxiliary valves, unit excitation systems, speed governors and work stations, control systems, service water units (pump and motor) for generator cooling, hydraulic cylinders for guide vanes and turbine discharge valves, oil-free self-lubricating bearing elements to the turbines and spherical valves.

14-MW Vacha-1 facility

The rehabilitation includes new 110-kV high-voltage equipment: disconnectors, circuit breakers, surge arresters, power lines protections for the Vacha -1 switchyard; and telecommunication equipment and electric metering equipment. Units 1 and 2 rehabilitation includes control and excitation systems, turbine governors, relay protections and other turbine equipment.
Procurement is expected to begin in the second quarter of 2017.

Source: hydroworld.com

MORE:

EPCG to invest EUR 700 million to build new renewables capacities, upgrade other facilities

Author: Vladimir Berbatović Source: Balkan Green Energy News https://balkangreenenergynews.com/epcg-to-invest-eur-700-million-to-build-new-renewables-capacities-upgrade-other-facilities/ State power utility Elektroprivreda Crne Gore (ЕPCG) will invest a total of EUR 700 million to build new renewable energy capacities and upgrade its other power generation facilities to bring them into line with environmental standards, with the aim of reducing dependence on imports due to hydrologic conditions,…


EPS to invest EUR 4.6 billion by 2027, EUR 700 million to go into hydropower, renewables

Author: Vladimir Spasić Source: Balkan Green Energy News https://balkangreenenergynews.com/eps-to-invest-eur-4-6-billion-by-2027-eur-700-million-to-go-into-hydropower-renewables/ Public power utility Elektroprivreda Srbije (EPS) intends to invest EUR 4.6 billion from 2019 to 2027, of which EUR 1.6 billion in the modernization of existing and construction of new thermal power plants (TPPs) as well as environmental protection, EUR 1,3 billion in distribution projects, EUR 1 billion…


Romanian hydropower company spends EUR 80 mln to refurbish 350MW power plant

Romania’s state-owned hydropower company Hidroelectrica will totally refurbish its hydropower plant (CHE) Râu Mare – Retezat under a EUR 80 million project, financed from own funds. The plan’s capacity will increase to 350MW after the process, Economica.net reported. The company wants to make CHE Râu Mare – Retezat the country’s largest supplier of system services,…