ERS opens 8.76 MW hydropower plant Bočac 2 under EUR 21.5 million investment - Hydro Balkans
+44 207 394 30 90 (London)

ERS opens 8.76 MW hydropower plant Bočac 2 under EUR 21.5 million investment

Main » novosti » ERS opens 8.76 MW hydropower plant Bočac 2 under…

Power utility Elektroprivreda Republike Srpske (ERS) yesterday unveiled the Bočac 2 hydropower plant (HPP) with an installed capacity of 8.76 MW and the expected annual output of 41.6 GWh of electricity. The project worth BAM 42 million (about EUR 21.5 million) is expected to break even within seven years.
Alongside HPP Bočac 2, which will create 32 jobs, a newly built small hydropower plant (SHPP) with an installed capacity of 586 kW close to HPP Bočac 1 was also unveiled. The SHPP will serve for the self-consumption of Hidroelektrane na Vrbasu, a subsidiary of ERS.

Hidroelektrane na Vrbasu, the direct investor in the project, states on its website that HPP Bočac 2 has no adverse impact on the environment, while it uses a clean and renewable energy source.

Laktaši-based Integral Inženjering carried out the construction works, while Banja Luka-based Elnos BL delivered equipment. The design, consultancy services, and supervision were provided by Belgrade, Serbia-based Jaroslav Černi institute for the development of water resources.

Hidroelektrane na Vrbasu General Manager Nedeljko Kesić said at the unveiling ceremony that the feasibility study projects annual revenues from the new HPP’s electricity sales at BAM 5.5 million (around EUR 2.81 million), local media reported.

HPP Bočac 2 is located 7 km downstream from HPP Bočac 1, which was built 37 years earlier.

The unveiling ceremony, held at the peak of election campaigning, was attended by Republika Srpska President Milorad Dodik, as well as Minister of Industry, Energy, and Mining Petar Đokić, who recalled that Republika Srpska has opened three energy facilities over the past few years – HPP Mesići-Nova, HPP Bogatići Nova, and HPP Bočac 2.

HPP Bogatići Nova on the Željeznica river near Sarajevo was put into operation exactly a month ago. The 9.96 MW HPP soaked an investment of BAM 18.5 million (around EUR 9.45 million). HPP Bogatići Nova should produce an average 46.26 million kWh of electricity annually.

HPP Bogatići Nova is expected to have annual revenues of BAM 5 million (about EUR 2.55 million).

The Mesići-Nova small hydropower plant (SHPP) near Rogatica, with an installed capacity of 5 MW, broke even on the BAM 10 million (EUR 5 million) investment after three and a half years of operation, Ljubomir Mrda, director of ERS subsidiary Elektrodistribucija Pale, said recently.

Source: balkangreenenergynews.com

MORE:

EPCG to invest EUR 700 million to build new renewables capacities, upgrade other facilities

Author: Vladimir Berbatović Source: Balkan Green Energy News https://balkangreenenergynews.com/epcg-to-invest-eur-700-million-to-build-new-renewables-capacities-upgrade-other-facilities/ State power utility Elektroprivreda Crne Gore (ЕPCG) will invest a total of EUR 700 million to build new renewable energy capacities and upgrade its other power generation facilities to bring them into line with environmental standards, with the aim of reducing dependence on imports due to hydrologic conditions,…


EPS to invest EUR 4.6 billion by 2027, EUR 700 million to go into hydropower, renewables

Author: Vladimir Spasić Source: Balkan Green Energy News https://balkangreenenergynews.com/eps-to-invest-eur-4-6-billion-by-2027-eur-700-million-to-go-into-hydropower-renewables/ Public power utility Elektroprivreda Srbije (EPS) intends to invest EUR 4.6 billion from 2019 to 2027, of which EUR 1.6 billion in the modernization of existing and construction of new thermal power plants (TPPs) as well as environmental protection, EUR 1,3 billion in distribution projects, EUR 1 billion…


Romanian hydropower company spends EUR 80 mln to refurbish 350MW power plant

Romania’s state-owned hydropower company Hidroelectrica will totally refurbish its hydropower plant (CHE) Râu Mare – Retezat under a EUR 80 million project, financed from own funds. The plan’s capacity will increase to 350MW after the process, Economica.net reported. The company wants to make CHE Râu Mare – Retezat the country’s largest supplier of system services,…


HPP BUK BIJELA

In March 2019 Serbia and Republika Srpska (RS) intend to jointly build the hydropower plant (HPP) Buk Bijela. The installed capacity of more than 180 MW, will equally contribute

to the energy stability of Serbia and the RS. HPP Buk Bijela will be built about 11.6 kilometres upstream from Foča. It is planned to be equipped with three hydro generators with

a total capacity of 93 MW, with the expected average annual electricity generation at around 330 GWh. The project would require an investment of EUR 193 million. Elektroprivreda Srbije (EPS) is currently reviewing the project for HPPs Buk Bijela, to be followed by determining the pace of implementation.

OVERHAUL OF DJERDAP 1,2 HPPS

At the end of 2017, EP S announced its intention to overhaul 10 units of HPP Đerdap 2 over 10 years, to help ex tend the plant ’s lifespan and boost its capacity by 50 MW. EPS and Siloviye Mashiny are cooperating on the overhaul of HPP Đerdap 1. The overhaul began in 2009. In Jul y 2018, the t wo companies signed a contract on the modernization of the A2 and A3 units in or der to complete the revitalization of the entire HPP in 2021.

CONSTRUCTION OF 2 SMALL HYDROPOWER PLANTS

EPS (Serbian state-owned power utility) plans the construction of 2 small hydropower plants on existing dams – SHPP Celije and SHP P Rovni. The project is a part of the programme for reconstruction of SHPPs through the loan of EBRD. The programme encompasses the reconstruction of 15 SHP Ps with total installed capacity of 18 MW. The project also includes the supply of electrical and mechanical equipment and their installation. Once the tender documents are signed, the works will be completed within 62 weeks.