HPP Đerdap 1’s overhaul to be completed in 2021, EPS says following signature with Russian contractor

Main » News » HPP Đerdap 1’s overhaul to be completed in…

Serbia’s state power utility Elektroprivreda Srbije (EPS) has signed the 10th addendum to an agreement on the revitalization of the Đerdap 1 hydropower plant (HPP) with Russia’s Siloviye Mashiny to complete the largest Serbian HPP’s overhaul, EPS said.
The revitalization of the A2 unit of the Đerdap 1 hydropower plant is planned to begin in September and last until mid-October 2019, while works on the A3 unit are to be completed in January 2021, EPS said.

The revitalization of the A1, A4, A5, and A6 units of Serbia’s largest hydropower plant, which has a total of six units, has been completed.

The overhaul of the Đerdap 1 hydropower plant was launched in 2009, Savo Bezmarević, executive director for energy production at EPS, recalled.

According to EPS acting General Manager Milorad Grčić, EPS “can” also cooperate with Silovye Mashiny on the overhaul of HPP Đerdap 2, which has 10 units.

The revitalization will boost the capacity of Đerdap 1’s units by about 10% and extend the HPP’s operating life by 40 years, EPS said, noting that the plant generates more than 5 billion kWh of electricity annually.

The USD 168 million investment is financed through the settlement of a USD 100.5 million clearing debt of the former USSR, while the rest is provided by EPS.

Đerdap 1 was put into operation 38 years ago and has produced 263 million MWh of electricity so far. Through to mid-May, Đerdap 1 generated 59% of electricity targeted for the entire 2018.

Source: Balkan Energy Green News

MORE:

IFC, North Macedonia to study hydro plant value

World Bank Group member IFC is to assess the value of a planned hydropower plant in Macedonia as part of an agreement recently signed with the Government of North Macedonia. The preliminary assessment on the Cebren project will assess the hydro plants value to the country and the region, including how it will help North…


Montenegro approves 33 mln euro loan guarantee for HPP Perucica overhaul

PODGORICA (Montenegro), August 2 (SeeNews) – Montenegro’s government has decided to issue a 33 million euro ($36.6 million) loan guarantee in a project for the overhaul of the 307 MW hydropower plant (HPP) Perucica, it said on Friday. The guarantee will cover a 33 million euro loan to be extended by German development bank KfW…


China’s AVIC offers to finance, build HPP Buk Bijela, 4 small hydropower plants

China National Aero-Technology International Engineering Corporation (AVIC) has expressed interest in the construction of three large hydropower plants (HPPs) – Buk Bijela, Foča, and Paunci – and four small hydropower plants (SHPPs), the Ministry of Energy and Mining said on its website. Energy and Mining Minister Petar Đokic met with potential partners from China –…