Natsionalna Elektricheska Kompania EAD is inviting tenders for rehabilitation of its 864-MW Chaira pumped storage hydro plant in Bulgaria - Hydro Balkans
+44 207 394 30 90 (London)

Natsionalna Elektricheska Kompania EAD is inviting tenders for rehabilitation of its 864-MW Chaira pumped storage hydro plant in Bulgaria

Main » novosti » Natsionalna Elektricheska Kompania EAD is…

Chaira is located in the Rila mountains about 100 km southeast of Sofia, the capital city. The underground power plant contains four reversible Francis pump-turbine units. Units 1 and 2 have been in operation since 1995, and Units 3 and 4 began operating in 1999. The upper compensating basin for Chaira is the Belmeken Reservoir.

NEK invites sealed tenders from contractors for supply and installation of plant and equipment. Tendering is open to firms from all countries.

For Chaira, the subject of the current tender is all activities and components of the engineering service, such as the design, manufacture, delivery, dismantling, repair-restoration, installation, designer supervision, adjustment, testing and commissioning of the facilities. Specific equipment cited include the turbine, governor, plant control and monitoring system, relay protections, unit excitation system, vibration monitoring and analysis system, 19-kV switchgear for the generator/motor and nodal 19-kV switchgear, technical water supply pumps, electric energy metering systems, ventilation systems, and common auxiliary equipment and materials.

NEK received grant funds from the Kozloduy International Decommissioning Support Fund toward the cost of rehabilitating its Belmeken-Sestrimo-Chaira hydro complex and the Vacha-1 110-kV switchyard. Additionally, NEK will use its own funds to complete the work.

The Belmeken-Sestrimo-Chaira complex also includes the 375-MW Belmeken pumped storage project, 240-MW Sestrimo hydro plant, and 120-MW Momina Klissura hydro project.

In total, NEK owns 30 conventional hydro and pumped storage plant with a total installed capacity of 2,713 MW in generating mode and 937 MW in pumping mode.

Source: HydroWprld.com

MORE:

EPCG to invest EUR 700 million to build new renewables capacities, upgrade other facilities

Author: Vladimir Berbatović Source: Balkan Green Energy News https://balkangreenenergynews.com/epcg-to-invest-eur-700-million-to-build-new-renewables-capacities-upgrade-other-facilities/ State power utility Elektroprivreda Crne Gore (ЕPCG) will invest a total of EUR 700 million to build new renewable energy capacities and upgrade its other power generation facilities to bring them into line with environmental standards, with the aim of reducing dependence on imports due to hydrologic conditions,…


EPS to invest EUR 4.6 billion by 2027, EUR 700 million to go into hydropower, renewables

Author: Vladimir Spasić Source: Balkan Green Energy News https://balkangreenenergynews.com/eps-to-invest-eur-4-6-billion-by-2027-eur-700-million-to-go-into-hydropower-renewables/ Public power utility Elektroprivreda Srbije (EPS) intends to invest EUR 4.6 billion from 2019 to 2027, of which EUR 1.6 billion in the modernization of existing and construction of new thermal power plants (TPPs) as well as environmental protection, EUR 1,3 billion in distribution projects, EUR 1 billion…


Romanian hydropower company spends EUR 80 mln to refurbish 350MW power plant

Romania’s state-owned hydropower company Hidroelectrica will totally refurbish its hydropower plant (CHE) Râu Mare – Retezat under a EUR 80 million project, financed from own funds. The plan’s capacity will increase to 350MW after the process, Economica.net reported. The company wants to make CHE Râu Mare – Retezat the country’s largest supplier of system services,…


HPP BUK BIJELA

In March 2019 Serbia and Republika Srpska (RS) intend to jointly build the hydropower plant (HPP) Buk Bijela. The installed capacity of more than 180 MW, will equally contribute

to the energy stability of Serbia and the RS. HPP Buk Bijela will be built about 11.6 kilometres upstream from Foča. It is planned to be equipped with three hydro generators with

a total capacity of 93 MW, with the expected average annual electricity generation at around 330 GWh. The project would require an investment of EUR 193 million. Elektroprivreda Srbije (EPS) is currently reviewing the project for HPPs Buk Bijela, to be followed by determining the pace of implementation.

OVERHAUL OF DJERDAP 1,2 HPPS

At the end of 2017, EP S announced its intention to overhaul 10 units of HPP Đerdap 2 over 10 years, to help ex tend the plant ’s lifespan and boost its capacity by 50 MW. EPS and Siloviye Mashiny are cooperating on the overhaul of HPP Đerdap 1. The overhaul began in 2009. In Jul y 2018, the t wo companies signed a contract on the modernization of the A2 and A3 units in or der to complete the revitalization of the entire HPP in 2021.

CONSTRUCTION OF 2 SMALL HYDROPOWER PLANTS

EPS (Serbian state-owned power utility) plans the construction of 2 small hydropower plants on existing dams – SHPP Celije and SHP P Rovni. The project is a part of the programme for reconstruction of SHPPs through the loan of EBRD. The programme encompasses the reconstruction of 15 SHP Ps with total installed capacity of 18 MW. The project also includes the supply of electrical and mechanical equipment and their installation. Once the tender documents are signed, the works will be completed within 62 weeks.