KESH adopts climate risk management plan - Hydro Balkans
+44 207 394 30 90 (London)

KESH adopts climate risk management plan

Главная » News » KESH adopts climate risk management…

Albania’s state-owned power utility KESH, whose production is almost entirely dependent on hydropower plants (HPP), has adopted its first climate risk management plan, a strategic approach to address the challenges posed by rising temperatures and increasing hydrological variability.
KESH operates a 1,350 MW hydropower cascade on the Drin River. It is facing challenges due to the impact of climate change and climate variability, which will require substantial investment in the near- and mid-term future, according to a news release.

In preparation for this, the climate risk management plan defines a list of structural and non-structural adaptation measures that will be implemented by KESH to mitigate climate-induced risks but also to seize opportunities arising from climate change.

With the adoption of the plan, KESH will become one of the first hydropower operators in Europe to address the risks of climate change and climate variability through a formalized and strategic approach.

The plan was developed under a capacity-building program funded by the Austrian DRIVE fund and implemented by engineering and project management firm Pöyry together with the Swiss hydropower operator KWO.

The adoption of the plan is part of the terms of a EUR 218 million loan by the European Bank for Reconstruction and Development (EBRD) to KESH to support the company’s restructuring and transformation to a modern electricity generator operating in an electricity market that is being gradually liberalized, the EBRD said.

Agron Hetoja, CEO of KESH, said: “Building know-how in the field of climate resilient hydropower operation is an essential element of our strategy to sustain and further develop our position as a leading electricity generator in the Western Balkan region.”

According to earlier reports, KESH plans to build a floating solar power plant as part of efforts to diversify its energy mix. The floating solar power plant should be built on the Vau i Dejes reservoir, part of HPP Vau i Dejes, one of three HPPs in the Drin River Cascade.

Source: Balkan Green Energy

MORE:

The CEO of KESH will present a report on the renovation of 3 large HPPs

The CEO of KESH (Albanian public operator) – Mr. Agron Hetoja – will present a report on the renovation of 3 large HPPs on the river Drin, with the capacity of 1.350 MW, including Fierza HPP, Komani HPP, and Vau i Dejës HPP. The is trustworthy information. They will also probably dwell upon the construction…


Natsionalna Elektricheska Kompania EAD presents hydropower investment projects at the Summit «Hydropower Balkans 2017»

Bulgarian public NEK EAD company-operator has confirmed the readiness to present a report on rehabilitation and modernisation of 5 HPPs: Chaira 844 MW, Belmeken 74 MW, Sestrimo 240 MW,  Momina Klisura 120 MW, Vacha 14 MW. Overall investment volume is € 37m.


China’s Dongfang shows interest in construction of Dabar HPP in Bosnia

SARAJEVO (Bosnia and Herzegovina), July 6 (SeeNews) – China’s Dongfang Electric Corporation is interested in the construction of the 160 MW Dabar hydro power plant (HPP) in Bosnia, the Balkan country’s Foreign Investment Promotion Agency (FIPA) said on Thursday. Representatives of Dongfang have submitted a letter of intent for this project to the government of…