Last month, the tiny Balkan nation of Kosovo narrowly avoided an energy crisis by reaching a deal with two private property owners to access some of the lignite coal it needs to supply its power plants. Several weeks earlier, the state-owned power company, KEK, had come dangerously close to running out of coal after villagers living near the reserves requested more money to resettle.

The situation had raised the question of whether Europe’s newest nation might be on the edge of a complete energy collapse, as KEK only possessed two weeks’ worth of reserves. It exposed the extent to which many developing countries still depend on coal as the most cost-efficient resource to meet their energy needs. Furthermore, it demonstrates how despite recent restrictions on funding for coal plants, institutional investors like the World Bank – which has been funding a new lignite coal-fired power plant in Kosovo – sometimes decides that, in rare cases, fossil fuels are the only feasible option.

Economics of coal

There are many economic arguments at play when discussing Kosovo’s energy security and the benefits of coal. One of them being that Kosovo sits on the 5h largest reserve of lignite coal in the world. Given the counties experience in mining this fossil fuel, and the reliability of this energy source, it makes sense to continue with what they know. Transitioning to green energy sources will take political will. Even wealthier countries like Germany have struggled to achieve the transition to a low-carbon energy system based mainly on renewables – and at 40% of the country’s energy mix, coal still accounts for the backbone of its energy supply.

There are also a number of challenges unique to Kosovo that have led to continued investments in the coal sector. As the World Bank was examining plans to create a new, updated coal plant, Kosovo was still relying on two lignite coal power plants, which are 47 and 36 years old, to service 97% of the country’s energy needs. Due to current inefficiencies in coal production, energy theft and an outdated grid, blackouts remain a fact of life for many Kosovars and are a major drag on the economy.

According to government figures, unreliable supplies are estimated to account for private sector losses of £251 million every year, or about 4% of the country’s GDP. It was due in large part to these lingering discrepancies that in 2011, the World Bank concluded in a report that Kosovo’s rising energy needs could only be met cost-effectively by building a new, updated coal plant. One of the independent reviewers of the report, Professor Wladyslaw Mielczarski, said that despite the fact that wind and solar prices have since decreased rapidly, “very little has changed” and coal remains the only viable choice for Kosovo.

There is a consensus that Kosovo’s energy crisis needs to be resolved – and quickly – however, a coal dominated future has been challenged by Dr Daniel Kammen, professor at UC Berkeley. He believes energy security “can be created through investigation of new energy efficiency, renewable energy, and the wise use of fossil fuel resources”. And while Kosovars’ health is threatened by the pollution caused by out-dated coal plants, their lives are equally placed at risk by winter power outages.

African demands

While the energy crisis in a country like Kosovo is relatively unique, especially in a European country, similar dilemmas can be seen in Africa, where more than 600 million people still lack access to electricity. Despite the fact that countries such as Tanzania, Kenya, and Nigeria possess vast, largely untapped coal reserves, few of them, except for a few outliers like South Africa, have managed to exploit their resources.

Faced with the pressing need to quickly and affordably ramp up energy generation capacity in Africa, lawmakers such as Nigerian Finance Minister Kemi Adeosun and former UN leaders like Kofi Annan have urged governments and international bodies to adopt every available solution, from solar, to coal deposits to geothermal, to light up and power the continent. Speaking at the launch of the Africa Progress Panel’s latest report on the issue, Annan was among those to acknowledge the perceived hypocrisy of developed nations that have industrialized on fossil fuels and are now denying developing countries the same advantages. In July, for instance, Japan agreed to provide up to $6 billion to support power plant construction and clean coal technologies in partnership with the African Development Bank. The initiative will finance high-efficiency coal-fired plants that use clean coal technology to help meet Africa’s energy demand.

Despite the logic of relying on a broad base of energy solutions, both the World Bank and the EU have rendered it nearly impossible to consider financing coal power plants. In 2013, the bank placed restrictions on funding for coal power projects in “rare circumstances” to meet “basic energy needs in countries with no feasible alternatives.” The European Investment Bank followed suit shortly thereafter. In a rare example of more measured policy coming from the White House, the Trump administration has taken steps to address these discrepancies, announcing that it will encourage its delegates at the multilateral development banks (MDBs) to help countries access and use fossil fuels more cleanly and efficiently.

The Balkans’ latest energy crisis puts the spotlight on how developing countries in particular are likely to continue relying on carbon-based resources for base load power. A long drought and high temperatures across the Western Balkans slammed hydropower output and sent energy prices surging, forcing some countries such as Albania to import energy. Hopefully, with more measured policies and support from the MDBs, these states might soon have the capacity to weather such crises on their own.

Source: globalriskinsights.com

MORE:

Montenegro’s EPCG gets loan from Germany’s KfW for hydro plant overhaul

SARAJEVO (Reuters) – Montenegro power utility EPCG EPCG.MOT signed a 33 million euro ($36.5 million) loan deal with German state-owned development bank KfW [KFW.UL] on Wednesday to help fund the overhaul of three turbines at its 307 megawatt (MW) Perucica hydro power plant. The deal is a part of the KfW’s ongoing 80-million-euro Greening Public…


Consultant sought to help launch renewable energy auctions in Kosovo

Author: Balkan Green Energy News The European Bank for Reconstruction and Development (EBRD) has invited expressions of interest in providing it with consultancy services in order support the Government of Kosovo* in developing and implement a competitive scheme for the award of future support to renewable energy generators. The EBRD previously engaged with the Kosovo*…


Montenegro govt endorses concession deal with PM Hydro for HPP construction

PODGORICA (Montenegro), September 6 (SeeNews) – Montenegro’s government has approved a concession agreement with local company PM Hydro for the construction of a 995 kW hydro power plant (HPP), it said on Friday. The project envisages the construction of a hydro power plant on Vranjestica river in Kolasin municipality, which will produce 3.35 GWh of…


HPP BUK BIJELA

In March 2019 Serbia and Republika Srpska (RS) intend to jointly build the hydropower plant (HPP) Buk Bijela. The installed capacity of more than 180 MW, will equally contribute

to the energy stability of Serbia and the RS. HPP Buk Bijela will be built about 11.6 kilometres upstream from Foča. It is planned to be equipped with three hydro generators with

a total capacity of 93 MW, with the expected average annual electricity generation at around 330 GWh. The project would require an investment of EUR 193 million. Elektroprivreda Srbije (EPS) is currently reviewing the project for HPPs Buk Bijela, to be followed by determining the pace of implementation.

OVERHAUL OF DJERDAP 1,2 HPPS

At the end of 2017, EP S announced its intention to overhaul 10 units of HPP Đerdap 2 over 10 years, to help ex tend the plant ’s lifespan and boost its capacity by 50 MW. EPS and Siloviye Mashiny are cooperating on the overhaul of HPP Đerdap 1. The overhaul began in 2009. In Jul y 2018, the t wo companies signed a contract on the modernization of the A2 and A3 units in or der to complete the revitalization of the entire HPP in 2021.

CONSTRUCTION OF 2 SMALL HYDROPOWER PLANTS

EPS (Serbian state-owned power utility) plans the construction of 2 small hydropower plants on existing dams – SHPP Celije and SHP P Rovni. The project is a part of the programme for reconstruction of SHPPs through the loan of EBRD. The programme encompasses the reconstruction of 15 SHP Ps with total installed capacity of 18 MW. The project also includes the supply of electrical and mechanical equipment and their installation. Once the tender documents are signed, the works will be completed within 62 weeks.